The most powerful leadership skill an expert Project Manager needs for success

No one can be an expert in all fields. A Project Manager is a skilled expert on leading teams to initiate, plan, execute and close projects. These are among the most important skills, but not the most powerful. If you aren’t feeling well you go to see your General Practitioner (GP). Your GP understands the big picture and upon identifying a specific issue or risk with your health may refer you to a specialist. In this analogy the GP is like a Project Manager – they do not need to be an expert in every field and one difference between okay GP’s and excellent GP’s is the speed and quality and follow-up related to the referral. All Project Managers will tell you that the most commonly used skill on a project is communication. However, neither communication nor planning are the most powerful skills in the arsenal. The true multiplier, the most powerful skill, is the ability to learn from others. The ability to learn from others enables the PM to absorb the nuances of the culture, mitigate the hidden risks of the processes, and allow for the complexity of the technology. When a diverse project team gets together it doesn’t matter who is the smartest or most senior in the room. What matters is learning from everyone’s skills and experience and channeling that back to the team so the whole is greater than the sum. The most powerful leadership skill is the ability to apply the greater whole in order to reach the objectives of the project quicker and with less risk of failure.

Stephen Wise

https://www.IntegrationProfessionals.com 

How confident are you with the project forecast?

As every project progresses through it's lifecycle, the team’s forecast will evolve. The forecast value may move up or down, however, the accuracy of the forecast should always increase. The basis for increasing accuracy is that all estimates are forecasts with some level of uncertainty and as the project progresses the unknowns/uncertainty will decrease. This holds for forecasting any of duration, work effort, or cost. There are two important concepts in the below figure:  1)      We see the team’s forecast (solid middle line) moves up and down as time progresses; and,  2)      the range in value between the High

 and Low Estimate decreases in steps at each phase.

Estimated Value Progress Stephen Wise 

A key action for the Project Manager is to communicate to all stakeholders that early estimates have higher uncertainty. As part of communication with management and finance stakeholders, I usually ask for a reserve to be added onto my estimates based on the higher uncertainty of estimates and potential negative impact of risks. This amount can be progressively reduced and “given back” as the project progresses over time. Some types of projects inherently have high uncertainty during initiation and planning. For example, integration of custom software. When faced with projects involving high level of unknown, the Project Manger should use “Three-Point Estimating”. This technique will include the full range of possible values of the estimate and

 reduces bias that can lead to a highly optimistic or pessimistic estimate.

 

I usually create custom fields within Microsoft Project 2010 to capture and calculate the three point estimates. The approach is also called PERT. The formula is PERT Estimate = (Optimistic Estimate + 4 X Most Likely Estimate + Pessimistic Estimate) / 6.  Other project teams that work on a high number of similar projects will develop good enterprise knowledge for making estimates. An example would be an energy and gas company that knows 2 resources can lay pipe at 20 metres per hour and the material cost is $150 dollars per foot. Estimates in these situations can be very accurate, from an early stage. A Project Manager may have little control of the level of uncertainty or risk when handed a new assignment. However, appropriate application of the concepts above will lead to successfully managing and quantifying estimates of duration, effort, and cost. 

Stephen Wise

www.IntegrationProfessionals.com

Tags

tag agile excellence itil pmi prince2 project management baseline change request earned value issues methodology project manager schedule tools value wbs issue status leadership productivity project managment recovery scope turnaround ac ev pv benefits collaboration communicate communication culture data integrity drivers failures fast faster ideas investments mehtodology portfolio prioritizing project selecting speed sponsor success closure cost duration effort estimating execution forecast initiation lifecycle pert planning project 2010 risk three-point estimating work effort business challenge development disadvantage elite global growth hiring loyalty market perks race solutions staffing standards talent tb1 team unemployment brazil change china diversity employee environment factors fit hire mobile personnel skype tb4 turnover twitter virtual 90 days hires metric new on-boarding watkins challenges firms looking plan shifting tb9 work aging developed developing ethiopia germany japan population qualified skilled workers workforce certification economy experience gaps industries innovation intelligent knowledge modern quality sales soft skills tb2 education lack tb3 training business case implementation outcome Strategy customer dashboard executive long-term management results time closing executing flowers photography spring apology sorry stephen wise trudeau resilience Future-State Business-Value Transformation cybersecurity Merger healtcare IoT Artificial Intelligence Vision Clarity Decision-making skills Artificial Intelligence business solutions Business innovation with AI Transformative AI services drones tesla Mergers Synergy banking block chain cryptocurrency ledger middleman satoshi toronto AI in Supply Chain Sustainable Logistics Practices Omnichannel Supply Chain Management #AI #ai #entertainment #trends