rss

Stephen Wise Blog

Integration Professionals. We dramatically improve traction.

How confident are you with the project forecast?

the accuracy of the forecast should always increase

As every project progresses through it's lifecycle, the team’s forecast will evolve. The forecast value may move up or down, however, the accuracy of the forecast should always increase. The basis for increasing accuracy is that all estimates are forecasts with some level of uncertainty and as the project progresses the unknowns/uncertainty will decrease. This holds for forecasting any of duration, work effort, or cost. There are two important concepts in the below figure:  1)      We see the team’s forecast (solid middle line) moves up and down as time progresses; and,  2)      the range in value between the High and Low Estimate decreases in steps at each phase.

A key action for the Project Manager is to communicate to all stakeholders that early estimates have higher uncertainty. As part of communication with management and finance stakeholders, I usually ask for a reserve to be added onto my estimates based on the higher uncertainty of estimates and potential negative impact of risks. This amount can be progressively reduced and “given back” as the project progresses over time. Some types of projects inherently have high uncertainty during initiation and planning. For example, integration of custom software. When faced with projects involving high level of unknown, the Project Manger should use “Three-Point Estimating”. This technique will include the full range of possible values of the estimate and

 reduces bias that can lead to a highly optimistic or pessimistic estimate.

 

I usually create custom fields within Microsoft Project 2010 to capture and calculate the three point estimates. The approach is also called PERT. The formula is PERT Estimate = (Optimistic Estimate + 4 X Most Likely Estimate + Pessimistic Estimate) / 6.  Other project teams that work on a high number of similar projects will develop good enterprise knowledge for making estimates. An example would be an energy and gas company that knows 2 resources can lay pipe at 20 metres per hour and the material cost is $150 dollars per foot. Estimates in these situations can be very accurate, from an early stage. A Project Manager may have little control of the level of uncertainty or risk when handed a new assignment. However, appropriate application of the concepts above will lead to successfully managing and quantifying estimates of duration, effort, and cost. 

Stephen Wise

www.IntegrationProfessionals.com



Comments are closed.

Tags

brazil business change china culture diversity employee environment factors fit global hire loyalty mobile personnel skype speed success talent tb4 team turnover twitter virtual hiring staffing 90 days hires metric new on-boarding watkins challenges firms looking plan shifting standards tb9 work aging developed developing ethiopia germany japan population qualified skilled workers workforce customer dashboard executive long-term management project management results schedule sponsor strategy time benefits closing communication executing initiation Leadership planning project flowers photography spring apology sorry stephen wise trudeau issues prioritizing resilience cybersecurity Merger healtcare sales Artificial Intelligence drones tesla Mergers Synergy banking block chain cryptocurrency ledger middleman satoshi toronto AI in Supply Chain Sustainable Logistics Practices Omnichannel Supply Chain Management #ai #ai #entertainment #trends #sports #trends #ai #news #media #trends #logistics #1pager #integrationprofessionals #robotics #drones productivity project managment recovery scope turnaround agile excellence itil pmi prince2 ac baseline earned value ev pv wbs collaboration communicate data integrity drivers failures fast faster ideas investments mehtodology portfolio selecting challenge development disadvantage elite growth market perks race solutions tb1 unemployment certification economy experience gaps industries innovation intelligent knowledge modern quality soft skills tb2 education lack tb3 training change request risk business case execution implementation methodology outcome closure cost duration effort estimating forecast lifecycle pert project 2010 three-point estimating work effort project manager tools value #energy Future-State Business-Value Vision Clarity Decision-making skills IoT Artificial Intelligence business solutions Business innovation with AI Transformative AI services Transformation issue status #hospitality #parents #family 1pager